New-build aftercare: how subcontractors handle defects in the first two years

by The SubbieNow Team2 min read

Who fixes defects after handover: Handover – Buyer moves in; warranty starts; Years 1–2 – Builder warranty period: trade defects passed to subbies; Years 3–10 – Insurance period for structural defects

Handover isn't the end of a plot. For roughly two years after a buyer moves in, the housebuilder's customer care team will be calling about leaks, cracks, faulty sockets and sticking doors, and many of those calls land with the subcontractor who did the work. Run well, aftercare protects your reputation with the housebuilder. Run badly, it eats margin you never see.

Why the first two years?

Most new homes in the UK come with a structural warranty. Under NHBC Buildmark, for example, the first two years are the builder warranty period, when the housebuilder must put right defects that breach NHBC's standards. Housebuilders, in turn, pass trade-related defects to the subcontractor responsible. Check your subcontract for your exact obligations and response times.

What makes aftercare expensive?

ProblemEffect
Calls arrive by email, phone and textVisits missed or duplicated
No link to the original installCan't tell if it's your work
No photos from the visitCan't dispute the cause later
Engineers' diaries in their headsPoor first-time fix, repeat visits
Cost of visits never totalledNo idea what aftercare costs per site

How should subcontractors run aftercare?

  1. One intake: every call logged against the plot, with the housebuilder's reference.
  2. One calendar, per engineer, plus a list per site.
  3. Link to the original install: who did the work, when, with which materials.
  4. A form for every visit with photos, the fault, what was done and materials used.
  5. Categorise faults, so you can spot recurring causes: one fitting, one gang, one house type.
  6. Track the cost of each visit, and recover it where the cause isn't yours.

A worked example

Fictional example. A plumbing subcontractor gets three calls in a month about leaking waste joints on the same house type. Because every visit is categorised and linked to the original install, the pattern shows up straight away: the same fitting, installed by different gangs, all from one delivery batch. The supplier replaces the stock, and the remaining plots of that house type are checked before handover, avoiding further call-outs.

Where SubbieNow fits

SubbieNow's customer care module gives engineers a calendar and per-site list, forms with photo evidence, configurable fault codes and colour categories, and full history on completed jobs. Every job is linked to the plot and its original install, and customer care email addresses can be set per client. Engineers work from the mobile app.

Sources

See how aftercare closes the loop on our features page, or book a demo.

Frequently asked questions

Who is responsible for defects in a new-build home?

Under common new-home warranties such as NHBC Buildmark, the housebuilder is responsible for most defects in the first two years. Housebuilders usually pass trade defects back to the relevant subcontractor under their subcontract.

Should subcontractors charge for aftercare visits?

It depends on the cause and your subcontract. Genuine defects in your work are usually yours to fix; damage by the buyer or another trade often isn't. Evidence decides which it is.

How do you prove the cause of a defect?

With photos and notes from the visit, the original install record for the plot, and who worked there afterwards.