Ask most subcontractors how site ordering works and the honest answer is: an operative texts the office, the office rings the merchant, and three days later something arrives. Sometimes it's the right thing for the right plot. Often it's not, and the cost lands on the site as a whole, where no one can tell which plot or stage it belonged to.
Where does materials money leak?
| Leak | What happens | Fix |
|---|---|---|
| Orders with no plot | Cost can't be traced, plot P&L is wrong | Every order raised against a plot |
| Wrong-stage ordering | Second-fix items arrive at first fix and go walkabout | Orders tied to build stages |
| Duplicate orders | Two people order the same thing | Orders visible in one queue |
| Phone orders with no PO | Invoices you can't match | Purchase order for every approved order |
| Consumables mixed with materials | Fixings and PPE inflate plot costs | Separate consumables flow |
How should site ordering work?
- Operative requests from site: site, plot, build stage, items and quantities, and who it's for ("requested for").
- Office reviews in a single purchasing queue: approve, adjust or reject.
- Purchase order is generated and emailed to the supplier branch.
- Delivery is tracked against the order and plot.
- Cost lands on the plot, feeding plot-level P&L.
The operative still drives the request, because they know what the plot needs. The office keeps control of spend.
Why tie orders to build stages?
On housing sites, most materials belong to a stage of a particular house type. If an order can only include items for that plot's current stage, you avoid second-fix kit arriving at first fix, where it gets damaged, used elsewhere or lost. It also makes pre-ordering from the programme practical.
What about consumables?
Consumables such as fixings, sealant, blades and PPE don't belong to one plot. Running them as a separate, site-level flow keeps them out of plot costs and makes it easy to see what each site burns through.
A worked example
Fictional example. A plumbing and heating subcontractor used to place materials orders by phone. Moving to plot-tied ordering, an operative on plot 18 raises an order for second-fix items. The office notices plot 18 had the same order approved four days earlier, rejects the duplicate with a note, and the operative finds the original delivery in the garage. Over a site, catching a handful of these pays for the change.
Where SubbieNow fits
In SubbieNow, operatives raise orders against plot, record and "requested for" from the iOS app. Related build-stages logic keeps orders to the right stage, consumables run as their own site-level flow, and the office manages a purchasing queue that generates purchase orders and emails them to supplier branches.
See the full ordering flow on the features page, or book a demo.
Frequently asked questions
Should operatives be allowed to order materials directly?
They should be able to request them, because they know what's needed. Approval by the office before a purchase order goes out keeps spending under control.
What's the difference between materials and consumables?
Materials go into a specific plot (pipe, cable, boards). Consumables are used up across the site (fixings, sealant, blades, PPE) and are usually ordered at site level.
How do you stop materials being ordered for the wrong stage?
Tie orders to build stages and only allow items that belong to that stage for the plot's house type.