On a housing site, the final electrical stage is often valued only when the certificates are in. If the pack for plot 27 is missing one document, plot 27's final payment waits. Multiply that across a phase and certification becomes a cash-flow problem, not just a compliance one.
This checklist covers what is commonly included. Always follow BS 7671, your competent person scheme and the housebuilder's own handover requirements.
What goes in an electrical handover pack?
| Document | What it covers |
|---|---|
| Electrical Installation Certificate (EIC) | Design, construction, inspection and testing of the new installation, per BS 7671 |
| Schedule of inspections | The inspection checklist for the installation |
| Schedule of test results | Circuit-by-circuit test results |
| Building Regulations compliance certificate | Issued through your competent person scheme for notifiable work |
| Smoke, heat and CO alarm records | Commissioning records for alarm systems fitted |
| Certificates for extra systems | For example EV chargers or solar PV, where fitted |
| Manufacturer information | Instructions and warranties for consumer units and fittings, where the housebuilder asks |
Why do packs go missing?
- Test results are on a tester or a form at the van, not with the office.
- Certificates are produced weeks after the work, in a batch.
- Nobody can see which plots are complete and which are still missing a document.
- Variations (such as extra circuits) aren't reflected in the paperwork.
How do you get packs right every time?
- Certify per plot as you finish, not at the end of a phase.
- Store each document against the plot, so the pack builds itself.
- Track what's missing: a simple list of plots with incomplete packs, reviewed weekly.
- Link the pack to the application, so final stages aren't claimed without it, and are claimed as soon as it's complete.
- Keep operative competence visible, so the person signing is registered and in date.
A worked example
Fictional example. An electrical subcontractor finishes second fix on plots 40 to 47. The tester uploads results for each plot as it's done, and certificates are stored against each property. On Friday the office checks the certification list: plot 44 is missing its alarm commissioning record. It's completed on Monday, and all eight final stages go on the month-end application with their packs attached.
Where SubbieNow fits
SubbieNow tracks certifications with attached documents against sites and plots, and assembles certification packs from application data. Operative qualifications are held in the system, so the office can see who's competent for which job. Find out more on our electrical page, or see how it ties into applications for payment.
Book a 30-minute demo to see a handover pack built from a live plot.
Frequently asked questions
Who issues the Electrical Installation Certificate?
The competent person responsible for the design, construction and inspection and testing of the installation, following BS 7671 (the IET Wiring Regulations).
How is notifiable electrical work signed off in England?
Usually by an electrician registered with a competent person scheme (such as NICEIC or NAPIT), who notifies the work so the building control body and owner receive a compliance certificate. Check the current rules for your nation.
Why does the housebuilder want certificates before paying?
Because they need them to hand over the home and complete their own sign-offs. Missing certificates are a common reason a final stage is valued at zero.