Variations in construction: how subbies record them and get paid

The short answer

To get paid for a variation, record it on site when it happens: the plot, what changed, who instructed it, photos, and the extra materials and labour. Get the instruction confirmed in writing, price it, and add it as a separate referenced line on your next application for payment.

by The SubbieNow Team3 min read

Ask a subcontractor where their margin goes and "variations we never got paid for" is near the top of the list. Some are forgotten. Some are mentioned to a site manager and never written down. Some are agreed and then argued down because nobody can prove what was done. The answer isn't more paperwork; it's capturing the variation at the moment it happens.

What is a variation?

A variation is a change to the work you were contracted to do. On housing sites, common examples are:

  • Moving a boiler, socket or radiator position after first fix
  • Extra noggins, boxing-in or making good caused by another trade
  • A buyer upgrade added late (often handled as a sales extra)
  • A change of specification, such as a different tile or fitting
  • Returning to a plot out of sequence because the programme moved

Why do variations go unpaid?

ReasonWhat it looks likeFix
Never recordedDone on the day, forgotten by month-endLog it on site, on a phone, before leaving the plot
No instruction"The site manager said it was fine"Confirm in writing the same day
No evidenceWork is covered up by the next tradePhoto before and after
Not pricedLumped into "extras" with no breakdownMaterials and labour listed against the variation
Missed off the applicationSits in someone's notebookVariations flow into the application automatically

How should you record a variation on site?

Capture six things, every time:

  1. Plot and location: plot 23, en-suite.
  2. What changed: relocated basin waste 400 mm left to suit revised vanity unit.
  3. Who instructed it, and when: name, role and date.
  4. Photos: before and after, especially if it will be hidden.
  5. Materials used: so they can be costed.
  6. Labour time: who did it and for how long.

Then confirm the instruction by email or through your system, and price it promptly. A variation priced within a week is far easier to agree than one priced three months later.

A worked example

Fictional example. An electrical subcontractor is asked to add two external sockets to plots 30 to 35 after first fix. The operative logs a variation on each plot from the app, with photos of the new runs before plasterboard goes on and the materials used. The contracts manager adds the instruction reference from the site manager's email. At month-end the six variations, totalling £1,140, appear as their own lines on the application, each with photos. The QS approves them in the first round because there's nothing to query.

How do variations get into the application?

This is where spreadsheets fall down: the person who records the variation isn't the person who writes the application. In SubbieNow, variations are created on site or in the office with images, materials and labour breakdowns, linked to the plot, and pulled into Sales Applications as Variation lines. They also feed plot-level P&L, so you can see what each change actually cost.

Variations and the Construction Act

If a variation is in your application and the contractor intends to pay less than you claimed, they must give a pay less notice in time. Understanding payment notices and pay less notices helps you push back when a variation is simply left out of a payment without the right notice.

Quick checklist

  • Plot, location and description recorded on the day
  • Instruction confirmed in writing
  • Photos before and after
  • Materials and labour listed
  • Priced within a week
  • Listed separately on the next application

Variations are one of the main reasons subcontractors move off spreadsheets. See how they work in SubbieNow on our features page, or book a 30-minute demo on your own plots.

Frequently asked questions

What counts as a variation?

Any change to the work in your original order or drawings: extra work, omitted work, a different specification, or work in a different sequence that costs more.

Do I need a written instruction before starting a variation?

Check your subcontract. Most require a written instruction. At the very least, confirm a verbal instruction in writing the same day with the plot, description and who gave it.

Can I claim a variation after the work is finished?

Often you can, but it becomes much harder to prove. Recording it at the time, with photos and the instruction, is what gets it paid.