SubbieNow Book a Demo

Construction Act

Payment notices and pay less notices: Construction Act deadlines for subbies

by The SubbieNow Team3 min read

The dates that decide when you get paid: Day 0 – Payment due date; +5 days – Last day for the payment notice; −7 days – Pay less notice deadline, before the final date; +17 days – Final date for payment

The Construction Act (the Housing Grants, Construction and Regeneration Act 1996, as amended in 2011) gives subcontractors real protection on payment, but only if you know the dates. This is a plain-English guide to the payment cycle. It isn't legal advice: your subcontract may set different periods, and you should take advice on a dispute.

What are the key dates?

StepWhoWhen (default if the contract is silent)
Due dateSet by the contractUnder the Scheme for Construction Contracts: 7 days after the later of the end of the period or the making of a claim
Payment noticePayer (or a specified person)No later than 5 days after the due date, even if the sum is zero
Default payment noticePayeeIf no payment notice is given in time
Pay less noticePayerNo later than the prescribed period before the final date for payment: 7 days under the Scheme
Final date for paymentSet by the contractUnder the Scheme: 17 days after the due date

The payment notice deadline of 5 days after the due date is fixed by the Act. Many of the other periods can be set by the contract, which is why you need to read yours.

What is a payment notice?

A payment notice states the sum the payer considers due at the due date and how it was calculated. It must be given even if the amount is zero. Its job is to make it clear, early, what you'll be paid and why.

What is a pay less notice?

A pay less notice is required if the payer intends to pay less than the notified sum, for example because of a contra charge or a disputed variation. It must set out the sum the payer considers due and the basis of the calculation, and it must be given in time. If there is no valid pay less notice, the notified sum must be paid by the final date for payment.

A worked timeline

Fictional example, using the Scheme's default periods:

DateEvent
31 AugustPeriod end; application submitted the same day
7 SeptemberDue date (7 days later)
12 SeptemberLast day for the payment notice (5 days after the due date)
17 SeptemberLast day for a pay less notice (7 days before the final date)
24 SeptemberFinal date for payment (17 days after the due date)

If, on 20 September, the subcontractor hears that £2,000 is being held back for "snagging" with no pay less notice sent, that deduction is open to challenge.

What can you do if you aren't paid?

If the notified sum isn't paid by the final date, the Act gives a right to suspend performance after giving at least 7 days' notice, and disputes can be referred to adjudication. Both are serious steps: get advice first.

How good records help

Most payment rows are about evidence, not law. If your application is built from approved work submissions, referenced variations and listed contra charges, there is less for a payer to dispute and it's easier to show when a deduction has no proper notice. SubbieNow keeps those records on each plot and builds sales applications from them.

Sources

Want applications that leave less to argue about? Book a 30-minute demo.

Frequently asked questions

What happens if the contractor doesn't send a payment notice?

The payee can issue its own default payment notice (or its application may stand as one, depending on the contract), and the sum in it becomes payable unless a valid pay less notice is given in time.

Does the Construction Act apply to my subcontract?

It applies to most construction contracts in England, Wales and Scotland, including most subcontracts on housing sites. There are exceptions, for example contracts with residential occupiers for work on their own home. Check with an adviser if unsure.

Can a pay less notice be issued after the final date for payment?

No. It must be given no later than the prescribed period before the final date for payment. A late pay less notice is not valid.

Talk to us

Want a guided tour on your own programme?

30-minute walk-through. No commitment. Bring your live sites and we’ll show you SubbieNow on your data.

Book a Demo